Specific Management Plan Procedures
Separate procedures have been established for maintenance and construction
operations related to asbestos management. A single procedure has been
established for maintenance tasks, and this procedure is used both by
Facilities Operations (FO) and Housing and Dining Services (HDS). For
construction projects, Capital Planning and Development (CPD), FO and
HDS each have separate protocols.
Procedures used in Construction Projects
Because of the type and size of construction of project each department
has to manage, several differences can be observed when comparing the
following procedures. However, all have several traits in common. They
are: (1) Asbestos abatement is performed prior to the construction portion
of a project. (2) Care is taken to properly notify and train all persons
who may be exposed as a result of an abatement project, including those
in proximity to the abatement project who work for other employers, who
are tenants, or who are non-employees. (3) In projects in which an asbestos
abatement company is employed directly by a general contractor who is
responsible for the construction project to which abatement is related,
third party oversight is practiced. And (4), information related to asbestos
sampling and to asbestos abatement is specifically and strictly gathered
to maintain and support the WSU asbestos database. Construction procedures
are oriented toward proper management practices.
Procedures Used in Capital Planning and Development Projects
General Description of Capital Planning and Development (CPD) Projects
CPD projects usually pass through several distinct stages, including
pre-design (programming), design, and construction. Typically, each project
is developed by a designated project officer who is generally responsible
for the workings of the project, including the management of any hazardous
materials with which it may be associated. Should asbestos abatement be
necessary, it is carried out prior to construction of the project.
The design process may include schematic drawings, design development,
and finally, construction documents. Although hazardous materials management
requirements should be considered in the programming stage, it is especially
important to address them in the design process, either in the schematic
phase or the design development phase.
Each project requires either a written notice of the reasonable certainty
of non-disturbance of asbestos, or a good faith inspection is performed.
If there is reasonable certainty of non-disturbance of asbestos, a form
bearing the same title is filled out and signed by the project officer.
The "Reasonable Certainty of Non-Disturbance of Asbestos" form
is located in Appendix 1. A copy of this
document is provided to any general contractor bidding on the project.
If a good faith inspection is to be performed, the project officer may
select anyone listed in Appendix 5 to
perform it. An alternate individual or firm may be selected to perform
the good faith inspection after approval by EH&S. The project officer
should contact EH&S with the name, address and telephone number of
any individual or firm not appearing on the list in Appendix
5 at least one month prior to the date the good faith inspection is
to be performed. Following approval, the name of the alternate individual
or firm will be placed on the list in Appendix
5. EH&S periodically reviews the names of individuals and firms
on the Appendix 5 list to ensure they
meet regulatory requirements as inspectors, and to verify that the laboratory
used for sample analysis meets EPA and WAC requirements.
After the good faith inspection is performed, the report generated as
the result of the inspection is used to plan the management of asbestos-related
issues. In addition, the report is provided to any contractor bidding
on the project. The document is also provided to any WSU employees who
may be exposed during the abatement process or who may be working in areas
immediately adjacent to the project.
If the scope of the project changes after the good faith inspection is
performed, an additional good faith inspection must be performed in any
area not covered by the initial good faith inspection. If the scope of
the project changes after the project has been started, the project must
be stopped and a good faith inspection and abatement performed prior to
recommence of the project.
Asbestos abatement precedes project work as a general policy at WSU.
An exception is the rare situation that demolition of the portion of a
structure must be done in order to be able to access the asbestos, and
the asbestos abatement contractor cannot perform the demolition. In this
instance, close cooperation between the general contractor and asbestos
abatement contractor is monitored by a third party overseer to safely
coordinate the activity.
If asbestos is discovered during the construction phase of the project,
the area where it is discovered is isolated and a certified asbestos
abatement crew or contractor is brought in to establish a regulated area
and properly deal with the asbestos before construction is resumed. Note
that friable asbestos materials, or non-friable materials made to release
asbestos fibers, must be reported to the Department of Ecology (DOE) and/or to the Washington Department
of Labor and Industries ten days prior to abatement if reportable amounts
are present. (NOTE: Ten calendar days to report to DOE; ten working days to report to Labor and Industries.)
During asbestos abatement, a third party oversees the activities of the
abatement contractor. The project officer may select approved third party
overseers from the list contained in Appendix
6. An alternate individual or firm may be selected to perform the
third party oversight after approval by EH&S. The project officer
should contact EH&S with the name, address and telephone number of
any individual or firm not appearing on the list in Appendix
6 at least one month prior to the date asbestos abatement is to be
performed. Following approval, the name of the alternate individual or
firm will be placed on the list in Appendix
6. EH&S periodically reviews the names of individuals and firms
on the Appendix 6 list to ensure they
meet regulatory requirements as inspectors and as asbestos supervisors,
and to verify that the laboratory used for sample analysis meets EPA and
WAC requirements. The third party overseer is responsible to provide services
as specified in Appendix 6.
The abatement contractor is certified by the State of Washington, and
meets all the regulatory requirements of the WAC asbestos rules. The abatement
contractor is required to conform to the specifications contained in Appendix
7. Note that if the abatement is performed in-house, the in-house
asbestos abatement procedures are use, listed below.
The third party overseer informs the project officer in writing of any
rule violations by the abatement contractor during the abatement process.
The third party overseer also performs pre-abatement and clearance sampling
of the abatement project. Finally, the third overseer provides a final report indicating that no asbestos-containing material remains
in the abatement area, or documents the nature of any unabated material.
Note: A Washington State-certified asbestos supervisor employed
by WSU, who is also an EPA-accredited asbestos building inspector, may
function as the third party overseer. Also note: The third party
overseer may not be in any way associated with the same company as the
asbestos abatement contractor, even if the overseer is listed in Appendix
6.
When abatement is completed, the third party overseer performs clearance
sampling and certifies the area is clean to the project officer. The project
officer then permits the clearance document to be given to the asbestos
abatement contractor, and the containment securing the abatement area
can be removed.
After the completion of the project, the abatement contractor provides
documentation of the abatement work completed to the third party overseer.
The third party overseer prepares and provides a report to WSU citing
specific areas where asbestos has been abated and certifying asbestos
is not present on abated surfaces.
Procedures Used in Facilities Operations Construction Projects
General Description of Facilities Operations Construction Projects
Facilities Operations (FO) performs three separate kinds of construction
projects: public works projects, internally logged WSU shop projects,
and work orders. FO public works projects are similar in nature to CPD
major capital construction projects since they typically involve design,
but they are usually on a much smaller scale. In FO public works projects,
independent contractors bid on the work to be performed, and asbestos
abatement may be part of the bid. Logged shop projects are performed
by WSU employees, and use the WSU asbestos abatement crew for any good
faith inspection and asbestos abatement needs. Work orders are usually
very small projects; they may also use the WSU asbestos abatement crew
for good faith inspection and abatement work.
Procedure
Each project requires either a written notice of the reasonable certainty
of non-disturbance of asbestos, or a good faith inspection is performed.
At the time a construction project is conceived or the project is conceptually
developed a decision is made as to whether or not design will be involved.
If design is involved, a FO architect, engineer or project leader will
ascertain whether or not there is reasonable certainty of non-disturbance
of asbestos, or whether a good faith inspection will be performed, and
will complete any needed forms or statements. If the project is a log
with no design, or is a no log work order, the construction supervisor
will complete any necessary forms.
If there is reasonable certainty of non-disturbance of asbestos on a
logged project, the "No" box on the "Safety Hazard Checklist"
for the Log is checked. Alternately, the "No" box on the "hazard
list" on the No Log Work Order form is checked. If the project is
a public works project, a "Reasonable Certainty of Non-Disturbance
of Asbestos" form is filled out and signed by the project officer.
This form is provided to each bidder on the project. An example of a "Reasonable
Certainty of Non-Disturbance of Asbestos" form is located in Appendix
1.
If the "Yes" box is checked on either the log or no log forms,
the architect, engineer, project leader or construction supervisor copies
the form and sends it to the Operations Center Supervisor, Maintenance
Services Division. The Operations Center Supervisor, or an employee working
directly for the Operations Center Supervisor will coordinate with the
architect, engineer, project leader or construction supervisor, and will
arrange for a good faith inspection of the project. Alternately, the WSU
asbestos database will be checked, and if sample result(s) are found for
materials which may be disturbed during the project, the page(s) containing
the result(s) are copied. The results of the good faith inspection, or
the copied asbestos database page, are attached to the log or no log "Safety
Hazard Checklist" form and returned to the architect, engineer, project
leader or construction supervisor.
If a good faith inspection is to be performed, an accredited member of
the WSU asbestos abatement crew may perform it. As an alternative, anyone
listed in Appendix 5 may be selected
to perform the good faith inspection. Any additional individual or firm
may be selected to perform the good faith inspection after approval by
EH&S. The architect, engineer or construction supervisor should contact
EH&S with the name, address and telephone number of any individual
or firm not appearing on the list in Appendix
5 at least one month prior to the date the good faith inspection is
to be performed. Following approval, the name of the alternate individual
or firm will be placed on the list in Appendix
5. EH&S periodically reviews the names of individuals and firms
on the Appendix 5 list to ensure they
meet regulatory requirements as inspectors, and to verify that the laboratory
used for sample analysis meets Department of Ecology and WAC requirements.
After the good faith inspection is performed, the report generated as
the result of the inspection is used to plan the management of asbestos-related
issues. If the project is a public works project, the good faith inspection
document is provided to any bidding contractor. This good faith inspection
document is also provided to any WSU employees who may be working in areas
immediately adjacent to the project or who may be exposed during the abatement
process.
If the scope of the project changes after the good faith inspection is
performed, an additional good faith inspection must be performed in any
area not covered by the initial good faith inspection. If the scope of
the project changes after the project has been started, the project must
be stopped and a good faith inspection and abatement performed prior to
recommence of the project.
Asbestos abatement precedes project work as a general policy at WSU.
An exception is the rare situation that demolition of the portion of a
structure must be done in order to be able to access the asbestos, and
the asbestos abatement contractor cannot perform the demolition. In this
instance, close cooperation between the general contractor and asbestos
abatement contractor is monitored by a WSU third party overseer, to safely
coordinate the activity.
If asbestos is discovered during the construction phase of the project,
the area where it is discovered is isolated, and a certified asbestos
abatement crew or contractor is brought in to establish a regulated area
and properly deal with the asbestos before construction is resumed. Note
that friable asbestos materials, or non-friable materials made to release
asbestos fibers, must be reported to DOE and/or to the Washington Department
of Labor and Industries ten days prior to abatement if reportable amounts
are present.
Except in public works contracts, asbestos abatement will be performed
by the WSU asbestos abatement crew, unless specifically called out for
the project by the architect, engineer, project leader or construction
supervisor. If the WSU asbestos crew performs abatement, the supervisor
of the crew shall be accredited by DOE as an asbestos building inspector,
and shall be certified as an asbestos supervisor by the State of Washington.
After abatement is completed, the supervisor of the WSU asbestos crew
provides information to EH&S as specified in the "Good Faith
Inspection Criteria" in Appendix 5.
In public works contracts, as well as in special situation project logs,
asbestos abatement may be performed by a subcontract to a general contractor.
For any asbestos abatement project performed by an asbestos abatement
contractor, a third party oversees the activities of the asbestos abatement
contractor.
The abatement contractor is certified by the State of Washington, and
meets all the regulatory requirements of the WAC asbestos rules. The abatement
contractor is required to conform to the specifications contained in Appendix
7.
The third party overseer informs EH&S in writing of any rule violations
by the abatement contractor during the abatement process. The third party
overseer also performs pre-abatement and clearance sampling of the abatement
project. Finally, the third party overseer provides a final report indicating that no asbestos-containing material remains in the
abatement area, or documents the nature of any unabated material. Note:
A Washington State-certified asbestos supervisor employed by WSU, who
is also an EPA-accredited asbestos building inspector, may function as
the project overseer. Also note: The third party overseer may not be in
any way associated with the same company as the asbestos abatement contractor,
even if the overseer is listed in Appendix
6.
When abatement is completed, the third party overseer performs clearance
sampling and certifies the area is clean to the architect, engineer or
construction supervisor. The architect, engineer or construction supervisor
then permits the clearance document to be given to the asbestos abatement
contractor, and the containment securing the abatement area can be removed.
After the completion of the project, the abatement contractor provides
documentation of the abatement work completed to the third party overseer.
The third party overseer prepares and provides a report to WSU citing
specific areas where asbestos has been abated and certifying asbestos
is not present on abated surfaces.
Procedures Used in Housing and Dining Services Construction Projects
General Description of Housing and Dining Services Construction Projects
Housing and Dining Services (HDS) performs construction projects of various
sizes. Larger projects are given to Capital Planning and Development (CPD) or to Facilities Operations (FO), where
they go through the previously defined procedures for asbestos management. Smaller projects
are performed by departmental staff.
Procedure
Each construction project performed by HDS staff requires either a written
notice of the reasonable certainty of non-disturbance of asbestos, or
a good faith inspection is performed. The supervisor for the specific
HDS area in which the construction project is to be done is responsible
for the evaluation of the project, and the determination of whether (a)
asbestos is involved in the construction project, and (b) if asbestos
is present, whether it will be disturbed.
If there is reasonable certainty of non-disturbance of asbestos, the
"No" box on the "Safety Hazard Checklist" for the
project is checked.
If there is not reasonable certainty, the "Yes" box on the
checklist is marked. A good faith inspection must then be performed. The
supervisor notifies the Maintenance and Construction Manager, Housing
Services who arranges for the good faith inspection.
If a good faith inspection is to be performed, an accredited member of
the WSU asbestos abatement crew may perform it. As an alternative, anyone
listed in Appendix 5 may be selected
to perform the good faith inspection. Any additional individual or firm
may be selected to perform the good faith inspection after approval by
EH&S. EH&S should be contacted with the name, address and telephone
number of any individual or firm not appearing on the list in Appendix
5 at least one month prior to the date the good faith inspection is
to be performed. Following approval, the name of the alternate individual
or firm will be placed on the list in Appendix
5. EH&S periodically reviews the names of individuals and firms
on the Appendix 5 list to ensure they
meet regulatory requirements as inspectors, and to verify that the laboratory
used for sample analysis meets EPA and WAC requirements.
After the good faith inspection is performed, the report generated as
the result of the inspection is used to plan the management of asbestos-related
issues. The good faith inspection document is provided to any WSU employees
who may be exposed to asbestos released from the materials sampled. It
is also given to any employee working in areas immediately adjacent to
the project or who may be exposed during the abatement process.
Typically, asbestos abatement will be performed by the WSU asbestos abatement
crew, unless specifically called out for a project managed by a FO architect,
engineer or construction supervisor. If the WSU asbestos crew performs
abatement, the supervisor of the crew shall be accredited by EPA as an
asbestos building inspector, and shall be certified as an asbestos supervisor
by the State of Washington. After abatement is completed, the supervisor
of the WSU asbestos crew provides information to EH&S as specified
in the "Good Faith Inspection Criteria" in Appendix
5.
In public works contracts, as well as in special situation project logs,
asbestos abatement may be performed by a subcontract to a general contractor.
For any asbestos abatement project performed by an asbestos abatement
contractor, a third party oversees the activities of the asbestos abatement
contractor.
The abatement contractor is certified by the State of Washington, and
meets all the regulatory requirements of the WAC asbestos rules. The abatement
contractor is required to conform to the specifications contained in Appendix
7.
The third party overseer informs EH&S in writing of any rule violations
by the abatement contractor during the abatement process. The third party
overseer also performs pre-abatement and clearance sampling of the abatement
project. Finally, the third party overseer provides a final report indicating that no asbestos-containing material remains in the
abatement area, or documents the nature of any unabated material. Note:
A Washington State-certified asbestos supervisor employed by WSU, who
is also an EPA-accredited asbestos building inspector, may function as
the project overseer. Also note: The third party overseer may not be in
any way associated with the same company as the asbestos abatement contractor,
even if the overseer is listed in Appendix
6.
When abatement is completed, the third party overseer performs clearance
sampling and certifies the area is clean to the architect, engineer or
construction supervisor. The architect, engineer or construction supervisor
then permits the clearance document to be given to the asbestos abatement
contractor, and the containment securing the abatement area can be removed.
After the completion of the project, the abatement contractor provides
documentation of the abatement work completed to the third party overseer.
The third party overseer prepares and provides a report to WSU citing
specific areas where asbestos has been abated and certifying asbestos
is not present on abated surfaces.
Procedures Used in Maintenance and Custodial Activities
General Description of Maintenance and Custodial Activities Involving
Asbestos Containing Materials
Both Facilities Operations (FO) and Housing and Dining Services (HDS)
employ maintenance and custodial staff. Maintenance staff
in both departments may work in building mechanical rooms where surface-applied
materials or thermal systems insulation (TSI) are present. Maintenance
staff may move ceiling tiles which contain asbestos, or may affix equipment
or fixtures to floors, walls or ceilings which may contain asbestos-containing
material (ACM). Plumbers may work on systems insulated with ACM. Mechanics
may work on specific HVAC systems in mechanical rooms which may contain
ACM. In the motor pool, mechanics may be exposed to brake or clutch parts
which may contain ACM.
Custodians in both HDS and FO perform routine custodial tasks, such as
cleaning, waxing and buffing. Cleaning and buffing of floors containing
asbestos is common activity. Surfaces such as popcorn ceilings or suspended
tile ceilings may be cleaned.
Both custodians and maintenance employees may be confronted to damaged
or broken TSI, surfacing materials or ceiling tiles which may be ACM.
Procedure
The supervisor of an employee at WSU is responsible to ensure that employee
is not inappropriately exposed to a health and safety risk, including
hazardous chemical substances such as asbestos fibers. The supervisor
must evaluate each task of the employee to determine if hazardous conditions
exist, then ensure the employee has proper training and protective equipment
and uses established procedures so that his/her health is not compromised.
Both WSU employees supervisors in maintenance and custodial departments
are trained annually in recognition of ACM and presumed asbestos-containing
material (PACM), and in procedures to be used if there is a release of
fibers from ACM or PACM.
When an employee's task is identified in which an ACM or PACM may be
disturbed by a maintenance or custodial employee, the supervisor makes
arrangements with EH&S and a member of the WSU asbestos crew or other certified asbestos worker(s) to have the task performed with monitoring for exposure. Sampling of the material is done, and a
record of environmental conditions during the task is made. Air monitoring is performed during the task, and the employee
is informed of the results of monitoring. This information is used to
develop either a positive exposure assessment (PEA) or a negative exposure
assessment (NEA), depending on the monitoring results. The exposure assessment
is placed in the Asbestos Management Plan, Appendix 3.
Any supervisor may refer to the Asbestos Management Plan with a query
about asbestos exposure during a specific task. If the task "closely
resembles the processes, type of material including percentage of asbestos,
control methods, work practices, and environmental conditions," the
employee may perform the task as indicated in any NEA. If there is a PEA for the task, it must be performed by the WSU asbestos crew or other certified asbestos worker.
If the task does not "closely resemble the processes, type of material
including percentage of asbestos, control methods, work practices, and
environmental conditions," then an exposure assessment is performed.
The supervisor contacts EH&S and a certified worker, as indicated above, to perform the assessment.
|